SYNOPSIS

This award winning landmark project with very tight construction schedule was completed on 18th July 2017, more than 5 months ahead of time with the Qlassic score of 81% and within budgeted cost. On top of that 5.5 million Total Man Hour without Loss Time Injury has been achieved.  Extraordinary architecture featured three (3) elevated high office towers, seven (7) levels of podium and one –level  sub-basement . All the three (3) blocks were supported by a series of inclined freestanding 2.0m   and 2.5m  diameter mega columns ranging from 28m to 40m in height, without any intermediate bracing.  These inclined freestanding mega columns were designed to support the transfer slab ranging from 1.2mto 1.8m thick at the height of 28m to 40m above ground level. For each tower the horizontal different from level 8 to rooftop was about 4.5m to 5.5m outward. This make the building structure inclined together with the unitized glass panel. Beside the inclination , the curvature façade creates the glass panel to be distorted.  This paper is highlighted the main challenges encountered and shared the many innovations created to overcome  these challenges:

- Foundation issues (Hard Rock Encounter)
- Inclined mega column
- Unitized Curtain Wall  on Twisted Facade


BIODATA OF SPEAKER

ZAINAL ABIDIN ABDULLAH

Project Manager
KLCC Projeks Sdn Bhd


Mr Zainal Abidin is a maestro in project management. Exceptional ability to manage and facilitate multi-disciplinary project teams and stakeholders. Among his proven track record is the successful delivery of the iconic landmark MACC New Headquarters project in Putrajaya. Currently, he is the Project Manager for a new development in Ampang, Kuala Lumpur. Graduated from University of Technology, Malaysia (UTM) in 1990 with Bachelor Degree in Civil Engineering. He has accumulated 30 years of working experience in the construction industry which includes IBS Specialist, Civil & Structure Consultant and Contractor.  



Limited to 470 participants only (first come basis) and invitation email will be sent for successful registration latest by 21 July 2020 @ 5.00 PM


Additional Information
Posted on
 
 
WEBINAR - Construction And Geotechnical Challenges For The SPRM New HQ Project In Putrajaya
Flyer

17-Jul-2020
Download
Post Comment
 
Member Type Normal Rate
(RM)
Online Rate
(RM)
Non IEM Member 47.17 47.17

For IEM members, please CLICK HERE to login for member rate
Rate stated does not include 8% SST
Non IEM Member will be charged an additional RM 20.00 Admin Fees inclusive 8% SST.




Advertisement


Advertisement

Advertisement

Advertisement
Survey Form


NEWSLETTER

Sign up for our newsletter to receive more information
Name:

Email Address:

Follow Us